To import machinery into Mexico, each machine is classified by its function, checked as new or used, its duty is worked out from the tariff line and the country where it was made, and, if it is for production, we look at whether IMMEX, PROSEC or Rule 8 (Regla Octava) brings the duty down. This guide covers everything from a single used backhoe to a complete packaging line: documents, taxes, standards, used equipment and the transport of heavy or oversize loads to the plant.
Main requirements
- An importer enrolled in Mexico’s importers’ registry (padrón de importadores), or a temporary import as a fixed asset of an IMMEX program. No registry? Our importer-of-record service can import for you.
- Invoice with make, model, serial number and, for used equipment, year of manufacture.
- Technical data sheet, photos of the machine and of its nameplate, and a description of what the machine does (the tariff classification depends on it).
- Packing list per piece when the machine travels disassembled or on several trucks.
- USMCA certification of origin if the machine was made in the United States or Canada and you want 0% duty.
- NOM certificate or exemption letter when the tariff line is subject to an electrical safety standard (see below).
How machinery is imported into Mexico, step by step
- Classification. Each machine is classified by function, almost always in chapters 84 and 85 of the Mexican tariff (TIGIE), with its NICO code. Duty, permits and standards all follow from the tariff line.
- New or used. Settled at the start, because it changes the requirements and how value is proved.
- Origin. What counts is where the machine was made, not where it was bought. A U.S.- or Canadian-made machine with USMCA certification pays no general duty; a Chinese-made machine bought in Texas pays the general duty of its tariff line.
- Regime. Definitive import, or temporary if it enters as a fixed asset of an IMMEX program or for a job and goes back.
- Documents. Invoice, data sheet, photos, packing list and, for used equipment, proof of ownership.
- U.S. side. Export filing in AES when the value per line exceeds $2,500; used self-propelled equipment is presented to U.S. Customs with its ownership documents at least 72 hours before crossing.
- Clearance and crossing. Pedimento in Nuevo Laredo; oversize loads cross at the World Trade Bridge or the Colombia Bridge depending on route and permit.
- Delivery. Transport, rigging and crane to your plant or job site.
Duties and taxes on machinery
- General import duty (IGI). Set by the tariff line: in chapter 84 many machinery lines are duty-free or pay between 5% and 15%. We confirm line by line before you buy.
- USMCA. Machinery originating in the United States or Canada, with a certification of origin, enters at 0% duty. The certification is issued by the producer, exporter or importer with the minimum data the agreement requires.
- Tariff increase since January 1, 2026. The decree published in the DOF on December 29, 2025 raised the general duty on 1,463 tariff lines for countries without a trade agreement with Mexico (China, Korea, India and others), with rates from 5% to 50%. Most lines are textiles, apparel, steel, plastics, auto parts, paper, footwear and aluminum, but before you buy Asian-made machinery we check whether its tariff line is on the list.
- VAT. 16% on the customs value plus duty and DTA. IMMEX companies with VAT/IEPS certification do not pay it out on temporary imports.
- DTA. Customs processing fee: 0.8% of the customs value on definitive imports; a fixed fee on IMMEX temporary imports.
- PROSEC and Rule 8. Manufacturers registered in a PROSEC sector program pay preferential duties on machinery and inputs for their sector; Rule 8 (tariff lines 98.02) allows, with a permit from the Ministry of Economy, the import of machinery and parts that would otherwise pay duty. See IMMEX vs PROSEC.
- You can estimate the taxes with our import tax calculator.
Industrial machinery and production lines
Besides construction equipment, we import industrial machinery every day for plants in Nuevo León, Coahuila, Tamaulipas and the Bajío: packaging and bottling lines (heading 84.22), food-processing equipment (84.38), plastic injection and extrusion machines (84.77), machine tools and CNC centers (84.56 to 84.65), presses, robots and machines with their own function (84.79), compressors (84.14), electric motors (85.01) and industrial furnaces (85.14). What changes compared with a single machine:
- A complete line in several shipments. A line that is dismantled and travels on several trucks can be classified as a single functional unit (Note 4 to Section XVI of the tariff) by the function it performs as a whole, even though it arrives in parts. It is planned before the first shipment, with a packing list per truck and the line diagram.
- Electrical safety standards. Much machinery with a motor or control panel falls in tariff lines subject to NOM-003-SCFI (electrical products up to 1,000 V) or NOM-001-SCFI (electronic equipment). A UL or CE mark does not replace the NOM.
- Production-process letter. Annex 2.4.1 (item 10, section VIII) allows machinery and equipment that will be used in the importer’s own production process and not sold to the public to be imported with a sworn letter, without meeting the commercial-information and labeling NOMs. Since October 2018 that letter no longer exempts safety NOMs, so a panel or machine in a tariff line with a safety NOM is certified or its classification is reviewed carefully.
- Spare parts and attachments. They are classified separately from the machine unless they travel with it as part of the unit; decide this beforehand, because duty and NOM change.
- Installation and start-up. If the manufacturer’s technicians are coming, time the machine’s arrival with their visit: the equipment can wait in our Laredo warehouse until the plant is ready.
Used machinery: what gets checked most
- Value. On used equipment customs looks harder at the declared value. Keep the purchase invoice, proof of payment and, if there is one, an appraisal.
- Identification. The nameplate with make, model, year and serial number must match the invoice and the pedimento.
- Permits. Some used goods need a prior import permit from the Ministry of Economy (Annex 2.2.1) and others have their own requirements by tariff line. Confirm before you buy, not when the machine is already in Laredo.
- Cleanliness. Used agricultural and construction machinery must arrive clean, with no soil or plant debris, because the plant-health authority (SENASICA) inspects it at the border.
- NOMs. If the tariff line is subject to a standard, used equipment meets it the same way; we check with the certification body whether an exception applies.
Construction equipment: skid steers, backhoes, excavators and forklifts
A single used machine, bought in the United States and delivered to a job site or a ranch in Mexico, is one of the requests we receive most. What makes it go smoothly:
- Declare the attachments. Buckets, forks, backhoe arms and other attachments go on the invoice one by one, with their value. Anything on the truck that is not on the invoice stops the crossing.
- Proof of ownership. Bill of sale or title, with the serial number that appears on the machine’s plate.
- The U.S. export. Used self-propelled equipment is presented to U.S. Customs with its ownership documents and export notice at least 72 hours before crossing. We handle it together with the Mexican clearance so both sides match.
- Who imports in Mexico. The buyer must be in the importers’ registry. If not, see our importer-of-record service.
- Delivery. Tell us the delivery address and whether the site has a way to unload. We coordinate the truck to the door.
Transporting heavy machinery and oversize loads
- Limits in Mexico. NOM-012-SCT-2-2017 sets the maximum weight and dimensions for federal highways. A machine over those limits travels with a special permit from the transport ministry (SICT) for indivisible heavy or oversize objects, with an authorized route and, when required, pilot vehicles.
- Limits in Texas. On the U.S. side an oversize load needs a state oversize/overweight permit (TxDMV) and escorts depending on width and height.
- Transport equipment. Lowboy or RGN for excavators and presses, extendable flatbed for long lines, crane at origin and destination. We quote from the data sheet: length, width, height and weight, and whether the machine can be broken down.
- Crossing. Dimensions decide the bridge and the time slot; the Mexican and U.S. permits must be ready before the machine reaches Laredo.
- Timing. Oversize permits take days, not hours. Tell us when you buy the machine, not when it is already on the truck.
Definitive or temporary import
On a definitive import the machine stays in Mexico and the import taxes are paid: the duty of its tariff line, VAT and the customs processing fee. On a temporary import, a company with an IMMEX program can bring in machinery as a fixed asset for its production while the program is in force, and equipment that enters for a specific job, a construction project or a trade show can go back when it is done without paying definitive taxes. Which one suits you depends on who owns the machine, how long it stays and what it is used for.
If the machine ships from Houston, see oilfield equipment and heavy machinery from Houston to Mexico. If it changes trucks at the border, see cross-dock and transloading in Laredo.
How we do it at Eilan
- We classify your machine in the Mexican tariff with its NICO code before the shipment leaves and tell you the exact duty by origin.
- We review the permits, NOMs and registries that apply to your tariff line and origin, and prepare the production-process letter when it applies.
- Clearance in Nuevo Laredo and U.S. export in Laredo by the same team, plus specialized transport, oversize permits and warehousing in Laredo, TX.
- If you are not yet in the importers’ registry, our importer-of-record service can import for you.
Frequently asked questions
Can used machinery be imported into Mexico?
Yes. Used machinery is imported every day. The requirements depend on the tariff line: some used goods need a prior permit from the Ministry of Economy, and what gets checked most is the declared value and that the machine matches its documents.
What taxes does machinery pay on entering Mexico?
The duty of its tariff line (many machinery lines in chapter 84 are duty-free or pay between 5% and 15%), 16% VAT and the customs processing fee. Machinery made in the United States or Canada with USMCA certification pays no general duty; machinery made in countries without a trade agreement may have had its duty raised since January 2026.
How much duty does Chinese-made industrial machinery pay?
The general duty of its tariff line, with no USMCA treatment even if bought in the United States. Since January 1, 2026 Mexico raised the duty on 1,463 tariff lines for countries without a trade agreement, with rates from 5% to 50%; most are textiles, steel, plastics and auto parts, but we check line by line before you buy.
What documents do I need to import a machine?
Invoice with make, model and serial number, data sheet, photos, packing list, certification of origin if you claim USMCA treatment and, in Mexico, the importers’ registry. For used equipment, also proof of ownership and year of manufacture.
Can I import a complete packaging or production line?
Yes. A line that travels dismantled on several trucks can be classified as a functional unit by the function it performs as a whole. It is planned before the first shipment with the line diagram and a packing list per truck, so that all the pedimentos match.
Does industrial machinery need a NOM certificate?
It depends on the tariff line. Much machinery with a motor or electrical panel is subject to NOM-003-SCFI or NOM-001-SCFI. The production-process letter exempts labeling and commercial-information standards, but since 2018 not safety standards.
What permits does heavy-machinery transport to Mexico need?
If the machine exceeds the weight or dimensions of NOM-012-SCT-2-2017, it needs a special SICT permit for indivisible objects with an authorized route; in Texas, a TxDMV oversize permit. Permits take days, so they are requested before the machine leaves.
Can I ship a single used machine, such as a skid steer or a backhoe, from the United States to Mexico?
Yes. The invoice lists the machine and each attachment, the buyer in Mexico must be in the importers’ registry, and used self-propelled equipment is presented to U.S. Customs with its ownership documents at least 72 hours before crossing.
This guide is informational. Requirements change with the tariff line, the origin and the regime; before each operation we confirm with you what applies to your case.